Harmony of the Seas
Iconic Mega-Ship Delivering World-Class Experiences at Sea
End‑to‑End Conversion Project Delivered with Precision and Scale
The approximately six-week project covered the full scope of design, manufacturing, demolition, and installation, focusing on upgrading a wide range of restaurant and bar venues across the vessel. While onboard installation works were carried out in spring 2026, the project timeline began much earlier, with design work initiated in April 2025 and production executed at LMG Finland during the summer of 2025.
)
Coordinated Logistics Power Complex Refit
At peak, more than 50 professionals were engaged across sites. Their expertise and dedication ensured that the project was delivered safely, on schedule, and to a high standard of quality. The onboard phase commenced with the careful demolition of existing spaces, followed by the installation and finishing of completely refurbished, modern guest-facing venues aligned with client requirements.
The scale of the project was also reflected in its logistics. A total of ten truckloads of prefabricated elements, bar counter modules, and installation materials were delivered to Cádiz, supported by four containers of consumables and tools. This coordinated logistics effort enabled efficient execution within a demanding timeframe.
)
Refurbished Venues
In total, ten restaurant and bar concepts were upgraded as part of the conversion:
Snowcone
Solarium Bistro
Crown Lounge
El Loco Fresh
Giovanni's Kitchen
Playmakers
Starbucks
Pesky Parrot
Casino Bar
Chef's Table
)
Equipment Delivery and Contribution
As part of the project scope, Loipart ensured that all equipment was delivered on time and fully prepared for installation. A wide selection of foodservice and galley equipment was supplied, including ice production and dispensing systems, professional coffee solutions, induction cooking equipment, and high-performance ovens. The delivery also featured specialized appliances such as rotisserie grills, pizza ovens, salamanders, dishwashing systems, and water-cooling units—supporting efficient and modern kitchen operations across multiple venues.
)
Strong Collaboration Behind the Success
The successful execution of the Harmony of the Seas conversion reflects close collaboration between design, production, logistics, and installation teams, supported by experienced project management throughout all phases.
As a result of this joint effort, the vessel now features modernized dining and bar facilities that enhance the overall guest experience and support future operational needs.
)
)
)
)
)
)
)